System message

Hydro Fehérvár

The newest aluminium recycling plant of Hydro Extrusion Hungary Kft. has been completed in Székesfehérvár, Hungary, capable of producing 90,000 tonnes of recycled aluminium per year, mainly for the premium automotive segment.
The building has a floor area of 20 000 m², including a three-storey office building of 400 m² per floor. One of the biggest challenges during the construction, which took almost two years, was the design of the casting pits. Their deepest point is 14 metres below the surface, so an additional 12 metres of steel pipe had to be installed. A diaphragm wall was constructed to manage groundwater, all under tight deadlines and by coordinating the work of several subcontractors.

The following comprehensive tasks were carried out during the construction:

  • excavation, deep foundations
  • monolithic and prefabricated construction
  • roof and façade cladding, insulation and mechanical works
  • electrical installations, cladding (PVC and resin)
  • painting and rendering
  • road construction, asphalting and paving, and utility network installation
  • glass and curtain walls, building automation, IT network and camera system installation
  • Installation of glass and curtain walls, building automation, IT network, and camera syste

In addition to consumer aluminium waste, the plant also processes scrap from the manufacturing process, so that the production of recycled aluminium is only 5% of the energy required for the original production. The investment has created 80 new jobs in the area.


Hydro's plant in Székesfehérvár is one of the most modern aluminium processing facilities in Europe, with six extrusion lines, advanced surface treatment technologies and more than 300 machining machines.


One of the biggest challenges of the project was the construction of the casting pits, the deepest point of which is at -14 metres and required an additional 12 metres of steel pipe to be driven down. A slurry wall had to be constructed to manage the groundwater, while meeting tight deadlines and coordinating subcontractors working in parallel was a major professional challenge.

SUBSIDIARIES

This webpage use cookies. Cookies stored on your computer.